Viewing Grant Proposal: Genesee County Drain Commissioner-Methane Gas Blowers
In order to lower electrical costs that GCDC-WWS plans to install gas blowers that utilize methane gas produced onsite via anaerobic digestion. This allows us to reduce our electrical use ~55% and replace it with the self-generated gas. This directly reduces the amount of energy the grid as a whole has to supply and maintain for our facility. This translates to a reduction of 176,463.1 kw/hr per month that the grid does not have to supply. This project will occur at our District 3 Wastewater Plant, serving residents, businesses and critical need facilities in Genesee County.